logoBC
Yaoundé - 25 April 2024 -
Economy

Phase 1 of Yaoundé-Douala Highway: CFHEC negotiates the third extension of deadlines

Phase 1 of Yaoundé-Douala Highway: CFHEC negotiates the third extension of deadlines
  • Comments   -   Friday, 21 August 2020 15:40

(Business in Cameroon) - The first phase (60 km) of the Yaoundé-Douala highway will not be delivered by December 30, 2020, as planned in the updated work schedule. Indeed, China First Highway Engineering Company Ltd (CFHEC), in charge of the construction, is negotiating a third extension of the deadline.

Works in the framework of the first phase of the 196-km road infrastructure started on October 13, 2014, and the initial duration was 48 months. However, the deadlines were first extended by 12 months (October 13, 2018, to October 12, 2019) and then by 14.5 months (October 13, 2019, to December 31, 2020).

According to Simon Pierre Mbousnoum, director of road investments at the Ministry of Public Works (Mintp), the new deadline being suggested is October 31, 2021. He further informs that this request has already been rejected by the Minister of Public Works Nganou Djoumessi. "The Minister of Public Works intends to check all the works the company would have performed by the end of the contractual deadline,” he says.

The reasons for this extension request

To justify this request, China First Highway Engineering indicates that the works were slowed down by delays in the clearance of rights-of-ways and bill payments. And justifiably so, according to figures disclosed by the Mintp, CFHEC is still owed XAF40.742 billion for its works. Of this amount, XAF38.956 billion has to be disbursed by Eximbank China and XAF1.785 billion counterpart funds by the State of Cameroon.

To disburse the fund, Eximbank China requests Cameroon to pay the counterpart fund and sign the document detailing the refund mechanism backing the construction project. On July 9, 2020, the Ministry of Economy sent the document to the Prime Minister’s office, according to Emmanuel Nganou Djoumessi. During the cabinet council of July 29, 2020, the latter explained that the signature of this document is a requirement provided in the loan agreement providing that once 70% of the loan has been disbursed, a refund mechanism should be signed by the two parties before any further disbursement is made.  

Apart from the financial and right-of-ways clearance reasons, the delay in meeting the agreed deadline is also due to the Covid-19 pandemic, the difficulties encountered during the demolition of rocky masses along the KP 40 and KP 60 and during the construction of earthworks on this same route.

Even if CFHEC meets the agreed deadline, phase 1 will not be commissioned before 2022 since its operationalization depends on the construction of two access roads over a 25-km route.

Access roads

The first road is a 10-km (2 X 2 lanes) structure through which users can reach KP 00 of the highway from the central post office located at the center of Yaoundé. The second access road will be 13 km long and will start from Bibodi (KP 60) to National Road No. 3 at Boumnyebel.

For the construction of these “additional works,” Cameroon has opted for a public-private partnership and negotiations are ongoing in that regard with China Communications Construction Company (CCCC), the parent company of CFHEC. This is confirmed by the Support Council for The Realization of Partnership Contracts (Carpa) but no one can tell how long the negotiations will last. "The CCCC has not even submitted its initial offer yet," a Carpa official informed.

Overall, notwithstanding the study currently being carried out by Scet/Tunisia and Louis Berger, "to reduce costs" and set the final amount of this work, everything suggests that the Phase 1 of Yaoundé-Douala highway would not be commissioned that soon.  

Baudouin Enama

noutchogouin-group-inaugurates-cfa5bn-animal-feed-production-plant-in-yaounde
Minister of Livestock, Fisheries, and Animal Industries (Minepia), Dr. Taïga, inaugurated a new modern and automated animal feed production plant in...
cameron-suspends-vessel-registrations-amid-ghost-ship-concerns-aims-for-digitization
Cameroonian Transport Minister Jean Ernest Massena Ngalle Bibehe issued a statement on April 22 announcing the suspension of registrations for vessels...
cameroon-s-aviation-safety-improves-yet-falls-short-of-international-targets
Transport Minister Jean Ernest Masséna Ngalle Bibehe issued a statement on April 22 detailing the results of a safety audit conducted by the International...
port-authority-of-kribi-eyes-cfa1-312bn-on-cemac-capital-market
The Port Authority of Kribi (PAK) plans to raise up to CFA1,312 billion (about €2 billion) over the next decade to fuel its development strategy. The...

Mags frontpage


Business in Cameroon n110: April 2022

Covid-19, war in Europe: Some Cameroonian firms will suffer


Albert Zeufack: “Today, the most important market is in Asia”


Investir au Cameroun n120: Avril 2022

Covid-19, guerre en Europe : des entreprises camerounaises vont souffrir


Albert Zeufack: « Le marché le plus important aujourd’hui, c’est l’Asie »